Lead time in inventory management: how to calculate it and plan around it
What lead time is, the simple formulas behind reorder points and safety stock, and how to use them before Q4 and the big markets.
The short answer
Lead time is the time between deciding to buy stock and having it ready to sell. For a wholesale brand it includes the supplier's production time, shipping, customs and receiving. You use it to set a reorder point: average daily sales × lead time in days, plus safety stock. Get lead time wrong and you run out of bestsellers just when retailers reorder.
Key points
- Lead time = order placed to stock on the shelf, not just the supplier's quoted production time.
- Reorder point = average daily sales × lead time (days) + safety stock.
- Track actual lead times per supplier; quoted and real often differ by weeks.
- Seasonal brands should plan Q4 and trade-show stock backwards from the sell date.
- Shorten lead time by ordering earlier, splitting shipments or holding key components.
What is lead time in inventory management?
Lead time is the total time from deciding to buy stock to having it on the shelf, ready to sell. For a home décor or gift brand buying from overseas makers, it usually includes:
- Order processing: placing and confirming the purchase order.
- Production: the maker producing your goods.
- Shipping and customs: ocean or air freight, port time and clearance.
- Receiving: checking goods in and putting them away.
Suppliers usually quote only the production time. Your real lead time is the whole chain.
How do you calculate lead time?
Lead time (days) = date stock is ready to sell − date the purchase order was placed.
Example: you place a purchase order on 1 March, the goods arrive on 18 April, and they're received and put away on 20 April. Your lead time is 50 days.
Track this for every purchase order. After a few orders you'll know each supplier's average lead time and how much it varies.
How does lead time set your reorder point?
Your reorder point is the stock level at which you should place the next order, so new stock arrives before you run out.
Reorder point = average daily sales × lead time (days) + safety stock
Example: a candle sells 12 units a day on average, the lead time is 50 days, and you hold 150 units of safety stock.
Reorder point = 12 × 50 + 150 = 750 units. When stock falls to 750, order again.
How much safety stock do you need?
Safety stock covers the days when lead time runs long or sales run hot. A simple formula:
Safety stock = (longest lead time − average lead time) × average daily sales
Example: your supplier's average is 50 days but the longest was 65. At 12 units a day: (65 − 50) × 12 = 180 units.
Hold more safety stock on bestsellers and lines retailers reorder often. Hold less on slow or seasonal lines you'd rather not be stuck with.
How do seasonal brands plan around lead time?
Most home décor, lifestyle and gift brands sell heavily into Q4 and write big orders at trade shows such as Atlanta Market and Las Vegas Market. Plan backwards from the date stock must be ready:
| Step | Example |
|---|---|
| Holiday orders ship to retailers from | 1 September |
| Stock must be received by | 20 August |
| Lead time (with buffer) | 75 days |
| Place purchase orders by | 6 June |
Then check the plan against what you sold last season, what retailers have pre-booked and what's already on order.
Five ways to shorten or steady lead time
- Order earlier for peak lines, especially before Q4.
- Agree split shipments, so part of an order arrives early.
- Hold long-lead components (glass, wicks, packaging) so production starts sooner.
- Use more than one supplier for your top sellers.
- Measure real lead times and share them with suppliers. What gets measured gets better.
Common lead time mistakes
- Using the supplier's quoted production time as your lead time.
- Planning with one average and no safety stock.
- Forgetting receiving time in a busy warehouse.
- Setting reorder points once and never updating them as sales change.
How salesorder.com helps
In salesorder.com, purchasing sits in the same system as your orders, stock and books:
- Purchase orders from stock levels, minimum stock and minimum order quantities, or straight from open sales orders, linked both ways.
- Earliest ship dates worked out from your purchase orders and their expected arrival, so you can tell retailers the truth about backorders and season prebooks.
- Forecasts from Mara. Ask Mara, salesorder.com's AI, to work out a forecast from your own sales data before every market and Q4, then check what's on order.
Ask Mara
Got a question about your own business?
Mara is salesorder.com’s AI. Ask her how this would work for the way you sell.
Questions
What is a good lead time?
There's no single number. What matters is that it's known and reliable. A steady 60-day lead time is easier to plan around than one that swings between 30 and 90 days.
What is the difference between lead time and cycle time?
Lead time runs from placing an order to having stock ready to sell. Cycle time is how long one step takes, such as manufacturing a batch. Lead time includes several cycle times plus waiting and shipping.
How much safety stock should I hold?
Enough to cover the gap between normal and worst-case lead time at your normal sales rate. A simple version: (longest lead time − average lead time) × average daily sales.
Can software tell me when to reorder?
Yes. In salesorder.com, purchase orders can be created from stock levels and minimums, or from open sales orders, and Mara can work out a forecast from your own sales before a busy season.